Capital Improvement Program

Project: Laroche-Delesseps Design Project No: TE0708 Status: Design/Pre-Construction Category: Traffic Improvements
Location: DeLesseps/LaRoche Start Year: 2003 End Year: N/A
Council District: N/A Project Manager: Barry Stanton, Stephen Henry BStanton@Savannahga.Gov; SHenry@Savannahga.Gov
Scope: To widen the corridor to provide pedestrian sidewalks on both sides of the street and bicycle facilities from Waters Ave to Skidaway Road.
Comments: 7/11/2019 6:14:22 PM:
Right-of-way acquisition process is ongoing.

4/5/2019 8:24:48 PM:
Right-of-way appraisals are ongoing, 13 parcels are ready for closing. ROW acquisition is projected to be completed June 2020, and ROW certification by October 2020. Bid selection process is anticipated for January 2021 with construction starting Spring 2021.

1/3/2019 4:57:25 PM:
Right-of-way appraisals are ongoing. ROW acquisition is projected to be completed June 2020, and ROW certification by October 2020. Bid selection process is anticipated for January 2021 with construction starting Spring 2021.

11/9/2018 10:46:32 AM:
Right of way was staked for the length of the property in August. Appraisals have begun with the expectation of 25 per month to done. ROW acquisition to be completed June 2020, and ROW certification by October 2020. Bid selection process is anticipated for January 2021 with construction starting Spring 2021.

7/11/2018 12:32:22 PM:
A property owners meeting was held by Real Estate Services to discuss Right-of-Way acquisition for this project. This meeting was on April 12 at the Southside Baptist Church between the hours of 5:00 and 7:00 pm. The City and council have approved the bid for the property appraisals. Property appraisals are expected to be completed by December 2018, ROW acquisition to be completed June 2020, and ROW certification by October 2020. Bid selection process is anticipated for January 2021 with construction starting Spring 2021.

6/12/2018 11:19:31 AM:
A property owners meeting has been scheduled by Real Estate Services to discuss Right -of -Way acquisition for this project . This meeting will be held on April 12 at the Southside Baptist Church between the hours of 5:00 and 7:00 pm. The City has received a bid for the property appraisals , which is currently being reviewed by the Economic Development department. Contract awarding is expected in June. Property appraisals are expected to be completed by December 2018, ROW acquisition to be completed June 2020, and ROW certification by October 2020. Bid selection process is anticipated for January 2021 with construction starting Spring 2021.

6/12/2018 11:19:31 AM:
A property owners meeting has been scheduled by Real Estate Services to discuss Right -of -Way acquisition for this project . This meeting will be held on April 12 at the Southside Baptist Church between the hours of 5:00 and 7:00 pm. The City has received a bid for the property appraisals , which is currently being reviewed by the Economic Development department. Contract awarding is expected in June. Property appraisals are expected to be completed by December 2018, ROW acquisition to be completed June 2020, and ROW certification by October 2020. Bid selection process is anticipated for January 2021 with construction starting Spring 2021.

1/11/2018 2:32:05 PM:
The Georgia Department of Transportation has approved the Right of Way agreement and has issued the City a notice to proceed. City will be submitting a request for property appraisal services and a meeting with the property owners along the DeLesseps / LaRoche Corridor will be scheduled in February of 2018.

11/3/2017 3:35:41 PM:
City is waiting for the approval by the Georgia Department of Transportation of the Right of Way agreement before proceeding with the Right of Way acquisition phase.

7/5/2017 11:55:58 AM:
Duplicate project. Remaining funds to be transferred to TE0305 (Laroche-Delesseps Widening) project

3/31/2017 12:08:38 PM:
Duplicate project. Remaining funds to be transferred to TE0305 (Laroche-Delesseps Widening) project

Last Project Update: 7/11/2019 6:14:24 PM
Fund(s): SPLOST IV (2003-08) | State Of Georgia | Contrbtn Frm Generl Fn
Project Financial Data Last Updated On: 7/26/2019 3:40:04 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$3,025,352.15 $1,298,967.49 $223,559.56 $1,502,825.10


1/11/2018 2:32:05 PM