Capital Improvement Program

Project: Eisenhower Drive Inter-Connect Project No: TE0611 Status: Design/Pre-Construction Category: Traffic Improvements
Location: Eisenhower Start Year: 2011 End Year: 2019
Council District: N/A Project Manager: Barry Stanton, Stephen Henry BStanton@Savannahga.Gov; SHenry@Savannahga.Gov
Scope: To install fiber-optic communication cable to inter-connect signals along the arterial and upgrade four signalized intersections
Comments: 7/11/2019 6:15:00 PM:
City surveyor is reviewing easement plat in preparation for recording.

4/5/2019 8:22:51 PM:
City surveyor is reviewing easement plat in preparation for recording.

1/3/2019 4:51:18 PM:
Real Estate Services is in the process of staking the proposed easements.

10/5/2018 4:01:05 PM:
Currently working on generating plats and deeds for the two locations.

7/11/2018 12:53:06 PM:
It has been determined that permanent utility easements are required at the NE and SW corners of the intersection of Eisenhower and Hodgson Memorial . The acquisition of the two miter easements has been deemed a condemnation by the Real Estate Services department, due to none responsiveness from owners. Condemnation expected to take 60-90 days, completion in September 18. Signal poles will be ordered upon completed ROW, anticipated delivery in December 18'. Installation of Signal to begin Spring 19' with completion in Summer 19'

6/12/2018 11:23:54 AM:
It has been determined that permanent utility easements are required at the NE and SW corners of the intersection of Eisenhower and Hodgson Memorial . The acquisition of the two miter easements is being coordinated by the Real Estate Services department and estimated to be completed in July. An RFP for signal poles is expected to be released in August with construction beginning in the first quarter of 2019.

6/12/2018 11:23:54 AM:
It has been determined that permanent utility easements are required at the NE and SW corners of the intersection of Eisenhower and Hodgson Memorial . The acquisition of the two miter easements is being coordinated by the Real Estate Services department and estimated to be completed in July. An RFP for signal poles is expected to be released in August with construction beginning in the first quarter of 2019.

12/22/2017 10:27:48 AM:
Department has developed plans to upgrade the signalized intersection of Hodgson Memorial and Eisenhower Dr by the installation of mast arms , which will not require any right of way acquisition . It is estimated that quotes for the purchase of traffic signal poles and mastarms will be completed by the first quarter of 2018.

11/3/2017 3:30:25 PM:
We are in the process developing an upgrade for the traffic signal at the intersection of Hodgson Memorial and Eisenhower.

7/5/2017 11:53:13 AM:
We are in the process developing an upgrade for the traffic signal at the intersection of Hodgson Memorial and Eisenhower.

3/31/2017 12:08:38 PM:
Awaiting State Aid Funds

Last Project Update: 7/11/2019 6:15:02 PM
Fund(s): SPLOST V (2008-2014
Project Financial Data Last Updated On: 7/26/2019 3:40:04 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$360,000.00 $22,209.24 $0.00 $337,790.76


12/22/2017 10:27:48 AM