Capital Improvement Program

Project: 37th Street Corridor Signal Improvements Project No: TE0610 Status: Design/Pre-Construction Category: Traffic Improvements
Location: 37th Street Start Year: 2011 End Year: 2025
Council District: 1,2,3 Project Manager: Barry Stanton| Stephen Henry BStanton@Savannahga.Gov;SHenry@Savannahga.Gov
Scope: Provide signal improvements, pedestrian upgrades & dedicated left turn lanes
Comments: 4/7/2021 11:38:37 AM:
Revisions to the State Highway System were finalized on February 17,2020 which included changing 37th Street to a City Street. Options are being evaluated to use available funding toward designing and constructing parking stalls along sections of road where on-street parking encroaches on traffic lanes.

12/9/2020 5:26:58 PM:
Revisions to the State Highway System were finalized on February 17th, which included changing 37th Street to a City Street. Options are being evaluated to use available funding toward designing and constructing parking stalls along sections of road where on-street parking encroaches on traffic lanes.

8/6/2020 10:22:52 PM:
Revisions to the State Highway System were finalized on February 17th, which included changing 37th Street to a City Street. Options are being evaluated to use available funding toward designing and constructing parking stalls along sections of road where on-street parking encroaches on traffic lanes.

4/13/2020 9:24:41 AM:
Revisions to the State Highway System were finalized on February 17th, which included changing 37th Street to a City Street. Options are being evaluated to use available funding toward designing and constructing parking stalls along sections of road where on-street parking encroaches on traffic lanes.

12/23/2019 11:42:21 AM:
Revisions to the State Highway System are underway that will include changing 37th Street to a City Street. Once finalized, current available funding can be applied to designing and constructing parking stalls along sections of road where on-street parking encroaches on traffic lanes. This would be the first phase of improvements. Additional funding will be needed for intersection improvements and signal upgrades.

10/2/2019 8:35:21 AM:
Revisions to the State Highway System are underway that will include changing 37th Street to a City Street. Once finalized, current available funding can be applied to designing and constructing parking stalls along sections of road where on-street parking encroaches on traffic lanes. This would be the first phase of improvements. Additional funding will be needed for intersection improvements and signal upgrades.

7/12/2019 10:52:31 AM:
Revisions to the State Highway System are underway that will include changing 37th Street to a City Street. Once finalized, current available funding can be applied to designing and constructing parking stalls along sections of road where on-street parking encroaches on traffic lanes. This would be the first phase of improvements. Additional funding will be needed for intersection improvements and signal upgrades.

4/5/2019 8:21:31 PM:
Revisions to the State Highway System are underway that will include changing 37th Street to a City Street. Once finalized, current available funding can applied to designing and constructing parking stalls along sections of road where on-street parking encroaches on traffic lanes. This would be the first phase of improvements. Additional funding will be needed for intersection improvements and signal upgrades.

1/3/2019 4:16:02 PM:
Awaiting State Aid Funding.

10/2/2018 4:45:07 PM:
Awaiting State Aid Funding

6/26/2018 8:50:03 AM:
Awaiting State Aid Funding

3/30/2018 9:22:32 AM:
Awaiting State Aid Funding

3/30/2018 9:22:32 AM:
Awaiting State Aid Funding

1/11/2018 2:25:25 PM:
Awaiting State Aid Funding

10/12/2017 5:34:09 PM:
Awaiting State Aid Funding

7/5/2017 11:39:52 AM:
Awaiting State Aid Funding

3/31/2017 12:08:38 PM:
Awaiting State Aid Funds

Last Project Update: 12/9/2020 5:27:00 PM
Fund(s): SPLOST V (2008-2014
Project Financial Data Last Updated On: 9/30/2020 3:07:44 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$340,000.00 $0.00 $0.00 $340,000.00


1/11/2018 2:25:25 PM