Capital Improvement Program

Project: Street Lighting Upgrade Project No: TE0607 Status: Design/Pre-Construction Category: Traffic Improvements
Location: Bay St. to Victory Dr. Start Year: 2011 End Year: TBD
Council District: N/A Project Manager: Barry Stanton, Stephen Henry BStanton@Savannahga.Gov; SHenry@Savannahga.Gov
Scope: Install street lighting in various locations
Comments: 7/17/2019 2:34:00 PM:
Due to GA Power's new requirement that the City must provide/manage the directional bores for the underground conduit, staff is evaluating options to install City-owned lighting.

4/5/2019 8:04:51 PM:
Coordinating with Georgia Power regarding installation of additional lighting. The number of lights required will be determined on photometric readings.

1/7/2019 2:25:56 PM:
Coordinating with Georgia Power regarding installation of additional lighting. The number of lights required will be determined on photometric readings.

10/5/2018 3:55:55 PM:
The project will now install decorative pedestrian lighting on Liberty St. and Oglethorpe Ave. The lighting will be designed and installed by GA Power. We are currently working on the limits of lighting installations.

7/17/2018 12:29:14 PM:
Project is on-hold, pending the construction of the Gwinnett St. Widening project (TE0709). This project will add median lighting to TE0709, which will be designed and installed by GA Power. Surplus money (if any), will be allocated to the installation of additional lights along Oglethorpe and Liberty Streets.

6/12/2018 11:32:09 AM:
The street lighting improvements on President St and McIntosh Blvd. between City Limits and Congress St are complete. Staff is moving forward with determining a plan for installation of additional lights along Oglethorpe and Liberty Streets.

6/12/2018 11:32:09 AM:
The street lighting improvements on President St and McIntosh Blvd. between City Limits and Congress St are complete. Staff is moving forward with determining a plan for installation of additional lights along Oglethorpe and Liberty Streets.

12/22/2017 10:19:33 AM:
Construction activities along President St as well as McIntosh Blvd. have progressed far enough to allow the contractor to complete eighty percent of the installation of the street lighting phase. It is anticipated that the street lighting for this project will be completed by the early part of 2018.

11/3/2017 4:41:11 PM:
Currently working on the installation of a new lighting system for the President St and McInstosh widening Project The two sections of the President St. lighting system have been completed

6/29/2017 4:26:20 PM:
Currently working on the installation of a new lighting system for the President St and McInstosh widening Project

3/31/2017 12:08:38 PM:
Ongoing; various locations.

Last Project Update: 7/17/2019 2:34:14 PM
Fund(s): SPLOST V (2008-2014) | Contrbtn Frm Generl Fn
Project Financial Data Last Updated On: 7/26/2019 3:40:03 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$1,000,000.00 $105,034.84 $0.00 $894,965.16


12/22/2017 10:19:33 AM