Capital Improvement Program

Project: President Street Improvements Project No: TE0310 Status: Implementation/Construction Category: Traffic Improvements
Location: President St & General McIntosh Blvd. Start Year: 2009 End Year: 2019
Council District: 1,2 Project Manager: Roger Raines RRaines@Savannahga.Gov
Scope: Stormwater, water, sewer and traffic improvements at East President Street & General McIntosh Blvd.
Comments: 7/2/2019 3:12:38 PM:
Contractor McLendon continues to work thru the design and proposal with the City and its consultant Thomas & Hutton. Remainder of the project is complete and functioning well.

3/29/2019 2:29:31 PM:
Contractor McLendon is pricing the design/build sewage lift station for a change order request. Remainder of the project is complete.

12/31/2018 11:42:51 AM:
Punchlist work is essentially complete. The final traffic signal was activated for testing. McLendon has constructed part of the new forcemain. Consultant Thomas & Hutton is still designing the new lift station. Due to the scope increase, completion now scheduled for late 2019.

10/2/2018 2:35:16 PM:
Punchlist work continues. Thomas & Hutton is designing a sanitary sewer lift station and section of forcemain to use in lieu of a gravity sewer line which became unusable due to differential settlement.

7/12/2018 4:09:57 PM:
Construction of new installations complete. Final traffic shift completed. Change order work to install a new sanitary lift station/forcemain and installation of the last traffic signal is awaiting work by others. Punchlist work is underway. Punch list work scheduled for completion 4Q, 2018. Additional change order work necessary to complete sanitary sewer service for use by development is under design. Preliminary construction schedule for completion of this work is about April 2019.

6/12/2018 11:36:59 AM:
Construction of new installations complete. Final traffic shift completed. Milling and overlayment paving of street sections nearby and impacted by the construction to be paved in April under a new change order. Completion scheduled by 3rd quarter 2018.

6/12/2018 11:36:59 AM:
Construction of new installations complete. Final traffic shift completed. Milling and overlayment paving of street sections nearby and impacted by the construction to be paved in April under a new change order. Completion scheduled by 3rd quarter 2018.

12/27/2017 10:12:34 AM:
Minor paving, final traffic shift, and ancillary work all that remains to finish this project. Anticipate a second quarter 2018 completion date.

10/13/2017 12:38:20 PM:
Bilbo Bridge work continues as the final stage of construction continues. Project on schedule for completion early next year.

7/26/2017 12:16:37 PM:
Traffic shift completed placing traffic temporarily on the north half of the Bilbo Canal bridge as the south half of that bridge is completed. Sidewalks, crosswalks, and preparation for new traffic signals and street lights continue.

3/31/2017 12:08:38 PM:
Construction expected to be completed during the first quarter of 2018

Last Project Update: 7/2/2019 3:12:40 PM
Fund(s): 2009 Dsa TAD Bonds | W&S R&R Fund | SPLOST IV (2003-08) | SPLOST VI(2015-2020) | Miscellaneous | Rd Sales Tx Fund I | Road Sales Tax I
Project Financial Data Last Updated On: 7/26/2019 3:40:03 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$33,202,406.85 $32,581,344.92 $235,226.84 $385,835.09


12/27/2017 10:12:34 AM