Capital Improvement Program

Project: New Sidewalk Install Project No: SP0219 Status: Ongoing Category: Street Improvements
Location: City-wide Start Year: 2016 End Year: Annual
Council District: City-Wide Project Manager: Richard Spivey RSpivey@Savannahga.Gov
Scope: Install new sidewalks in areas where needed
Comments: 8/6/2019 4:01:39 PM:
No new sidewalk was placed in the 2nd quarter. A new sidewalk contract should be approved in August which will add a second contractor to work on sidewalks.

4/9/2019 10:30:57 AM:
In 2018 over 1400 feet of new sidewalk has been placed including the 53rd Street sidewalk through the Savannah Shines project.

1/22/2019 5:23:16 PM:
In 2018 over 1400 feet of new sidewalk has been placed including the 53rd Street sidewalk through the Savannah Shines project.

11/13/2018 6:56:46 PM:
New sidewalk is scheduled to be placed on 53rd street between Waters Avenue and Live Oak Street. This will be completed in the fourth quarter of 2018 as part of the Savannah Shines program.

7/4/2018 3:53:25 PM:
1,083 LF of new sidewalk has been placed through the second quarter of 2018. 600+ feet of new sidewalk was placed on Coffee Bluff Villa Road in the second quarter of 2018. This new sidewalk was placed at the community center to Coffee Bluff Road.

4/4/2018 5:57:21 PM:
Three hundred and twenty feet of new sidewalk has been placed so far in 2018.

4/4/2018 5:57:21 PM:
Three hundred and twenty feet of new sidewalk has been placed so far in 2018.

1/3/2018 10:40:18 AM:
New sidewalk has been placed on Waters Avenue between 52nd Street and 57th Street; Our three annual contractors have been focusing on the extensive backlog of sidewalk repairs at this time.

11/3/2017 5:06:10 PM:
New sidewalk has been placed on Waters Avenue between 52nd Street and 57th Street; Our three annual contractors have been focusing on the extensive backlog of sidewalk repairs at this time.

6/29/2017 4:01:44 PM:
Contract has been awarded. Staff is working with contractor to build new sidewalks.

3/31/2017 12:08:38 PM:
Staff to seek Council approval for new sidewalk repair and installation contract in March 2017

Last Project Update: 8/6/2019 4:01:39 PM
Fund(s): Contrbtn Frm Generl Fnd | SPLOST VI - District 5 Fund
Project Financial Data Last Updated On: 7/26/2019 3:39:58 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$245,644.28 $149,312.85 $0.00 $96,331.43


1/3/2018 10:40:18 AM