Project: Atwood Street Park Improvements Project No: RE0316 Status: Design/Pre-Construction Category: Parks and Recreation Improvements
Location: 202-210 Chatham St Start Year: 2015 End Year: 2019
Council District: N/A Project Manager: Carol Moon cmoon@Savannahga.Gov
Scope: Develop a park in the Atwood Street area.
Comments: 7/5/2019 9:20:47 AM:
Design and permitting of the project was successfully completed. On July 2nd City Council approved a contract with Johnson-Laux Construction for construction of a new pervious basketball court, pervious walkways, ADA parking and landscaping.

4/12/2019 12:23:44 PM:
FEMA approved the request to implement a basketball court, walkways, playground and landscaping on FEMA deed restricted properties. The design and permitting will be completed in the 2nd quarter.

1/2/2019 12:14:44 PM:
Staff continues to communicate and work with GEMA/FEMA to acquire necessary approvals for park development. FEMA approvals for open space requests can take 6-9 months. Design is underway and estimated to be completed in the 1st quarter.

10/5/2018 11:22:04 AM:
Staff continues to communicate and work with GEMA/FEMA to acquire necessary approvals for park development. FEMA approvals for open space requests can take up to 9 months.

7/12/2018 9:52:14 AM:
City staff submitted an application for a basketball court, walkway and playground on FEMA deed restricted properties. Staff continues to work with GEMA/FEMA to acquire necessary approvals for park development.

5/3/2018 12:26:06 PM:
Staff is waiting to hear from GEMA for approval of a basketball court.

5/3/2018 12:26:06 PM:
Staff is waiting to hear from GEMA for approval of a basketball court.

2/9/2018 1:11:24 PM:
City staff are working with GEMA/FEMA to acquire necessary approvals for tentative development plans.

Last Project Update: 8/2/2019 1:34:11 PM
Fund(s): SPLOST VI - District 4 Fund
Project Financial Data Last Updated On: 7/26/2019 3:40:16 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$255,000.00 $53,144.95 $37,011.50 $164,843.55


2/9/2018 1:11:24 PM