Project: Twickenham Greenspace Project No: RE0222 Status: Conceptual/Planning Category: Parks and Recreation Improvements
Location: Goebel Avenue Start Year: 2017 End Year: 2021
Council District: 3 Project Manager: Byron Stiles BStiles@Savannahga.Gov
Scope: Enhancements to Twickenham Greenspace will include a walking trail, bridges, benches, trash cans, lighting, ornamental plantings and a dog park.
Comments: 7/9/2019 11:24:10 PM:
Site survey work has been completed. Staff is working with our contract engineer on design details and preparation of construction drawings for review and approval.

4/5/2019 5:31:23 PM:
Site survey work has been completed. Staff is working with our contract engineer on design details and preparation of construction drawings for review and approval.

1/11/2019 5:05:30 PM:
New project. Staff is working with our contract engineer on design details and preparation of construction drawings for review and approval.

11/14/2018 9:05:27 AM:
CIP RE0222 was previously Holly Heights Greenspace. On September 13, 2018 City Council approved Amendment #6 which included Holly Heights Greenspace funding to be used to establish a Twickenham Greenspace capital account, resulting in RE0222 changing to Twickenham Greenspace. To date, staff prepared conceptual plans for the Twickenham Greenspace to include a walking trail, bridges, benches, trash cans, lighting, ornamental plantings and a dog park.

7/6/2018 11:55:11 AM:
The Holly Heights Master Plan was revised by relocating many elements to non-FEMA lots and removing the Community Center. The design phase is anticipated to commence July 2018 with construction starting by December 2018.

6/12/2018 11:33:39 AM:
A conceptual plan for park development includes a playground, shelter, community garden, basketball court and community center. Costs and concept options are being investigated and evaluated. Completion of initial design documents is expected in July.

6/12/2018 11:33:39 AM:
A conceptual plan for park development includes a playground, shelter, community garden, basketball court and community center. Costs and concept options are being investigated and evaluated. Completion of initial design documents is expected in July.

1/12/2018 3:05:55 PM:
Conceptual plan for park development has been done.The park would include playground,pavillion,basketball courts,community garden and community center.

11/15/2017 4:44:56 PM:
Conceptual master plan is being finalized to develop park to serve the needs of neighborhood.

6/28/2017 5:20:19 PM:
Currently in conceptual/design phase.

3/31/2017 12:08:38 PM:
Developing scope of work for master plan

Last Project Update: 7/9/2019 11:27:58 PM
Fund(s): SPLOST VI - District 3 Fund
Project Financial Data Last Updated On: 7/26/2019 3:39:57 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$116,836.80 $7,097.03 $0.00 $109,739.77


7/6/2018 11:55:11 AM