Capital Improvement Program

Project: Southside Park Development Project No: RE0124 Status: Design/Pre-Construction Category: Parks and Recreation Improvements
Location: Mohawk Lake and Joe Tribble Park Start Year: 2015 End Year: 2020
Council District: 6 Project Manager: Cristy Lawrence, Barry Baker CLawrence@Savannahga.Gov; BBaker@Savannahga.Gov
Scope: To develop park and recreation space for southside area (Mohawk Lake and Joe Tribble Park)
Comments: 6/21/2019 4:04:12 PM:
Design of Mohawk Park is complete and almost through the site permitting process. Project is currently being priced through state contract. The project will be constructed in two phases.

4/30/2019 9:01:30 AM:
100% drawings for Mohawk Park have been submitted for permit. Design for the approximately 27.2 acre park will include a walking trail, playground, fishing pier, dog park, shelter, parking areas, and restroom/maintenance building. Design and permitting should be complete by the start of the 3rd quarter 2019. The project will then be constructed in two phases.

1/9/2019 5:13:55 PM:
Survey was completed in 4th quarter of 2018. The design phase was kicked off in the 4th quarter of 2018 after the survey was completed. Design of the approximately 27.2 acres will include a walking trail, playground, fishing pier, dog park, shelter, parking areas, maintenance building, and restrooms. Design and permitting should be complete by the start of the 3rd quarter 2019. The project will then be constructed in two phases.

10/5/2018 9:39:44 AM:
A Mohawk Lake Park Master Plan was completed in 2nd quarter of 2018. A master plan for the approximately 27.2 acres reflects two phases of development and includes a walking trail, playground, fishing pier, dog park, shelter, parking areas, maintenance building, and restrooms. The survey work is currently under way and estimated to be completed in the 4th quarter. The design phase is anticipated to begin in the 4th quarter once the survey work is complete.

7/6/2018 11:40:57 AM:
A Mohawk Lake Park Master Plan was completed in 2nd quarter of 2018. A master plan for the approximately 27.2 acres reflects two phases of development and includes a walking trail, playground, fishing pier, dog park, shelter, parking areas, maintenance building, and restrooms. The design phase is anticipated to commence in the 3rd quarter of 2018.

4/17/2018 1:18:49 PM:
Conceptual plan for park development under review by staff.

4/17/2018 1:18:49 PM:
Conceptual plan for park development under review by staff.

1/16/2018 5:00:40 PM:
Conceptual plan for park development under review by staff.

11/15/2017 4:33:41 PM:
This project has been identified to be included in a RFP for Capital Project Management to manage.

6/30/2017 3:00:42 PM:
Developing scope of work for Request For Proposal.

3/31/2017 12:08:38 PM:
Developing scope of work for Request For Proposal.

Last Project Update: 8/2/2019 1:31:06 PM
Fund(s): SPLOST VI(2015-2020) | Contrbtn Frm Generl Fnd | SPLOST VI - District 6 Fund
Project Financial Data Last Updated On: 7/26/2019 3:39:56 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$1,299,112.78 $52,814.44 $104,266.25 $1,142,032.09


1/16/2018 5:00:40 PM