Capital Improvement Program

Project: Waters Avenue Corridor Improvements Project No: PD0309 Status: Implementation/Construction Category: Community Development Improvements
Location: Waters Avenue Start Year: 2008 End Year: 2019
Council District: 2,3,4 Project Manager: Doug Patten DPatten@Savannahga.Gov
Scope: Improve streetscape and business environment in the area
Comments: 7/3/2019 11:47:28 AM:
Phase II between Wheaton and Anderson Street has begun construction. Johnson-Laux is the contractor and the construction contract is $1,555,290.19. The project consists of removing and replacing the existing sidewalk, new accessible ramps, stamped concrete crosswalks, landscaping, and upgraded street lighting. Work began at Anderson Street and the contractor is working north.The work is over 70% complete and the scheduled completion is in the fall 2019. The contractor is currently ahead of schedule and the project may be completed earlier.

4/1/2019 1:34:44 PM:
Phase II between Wheaton and Anderson Street has begun construction. Johnson-Laux is the contractor and the construction contract is $1,555,290.19. The project consists of removing and replacing the existing sidewalk, new accessible ramps, stamped concrete crosswalks, landscaping, and upgraded street lighting. Work began at Anderson Street and the contractor will work north. Work is expected to be completed in the fall of 2019.

12/14/2018 1:41:02 PM:
Phase II of the project between Wheaton and Anderson Street is expected to begin construction in the early 1st Quarter of 2019. Construction is expected to take 10 months to complete.

10/9/2018 2:39:11 PM:
Staff met with neighborhood groups in July 2018. Plans are currently in permitting. Final plans are expected in October 2018. Construction is expected to start in the first quarter of 2019.

6/26/2018 10:07:04 AM:
Phase I (37th Street to Anderson St.) is complete. Staff walked Phase I on June 26, 2018. Plans for Phase II (Anderson St. to Wheaton St.) have been updated and are currently in permitting. Staff plans to meet with neighborhood groups in July 2018. It is anticipated that final plans and permits will be available in July 2018. Construction is expected to start in Fall 2018 and completed in Summer 2019.

6/12/2018 11:18:31 AM:
Phase I (37th Street to Anderson St.) is complete. Plans for Phase II (Anderson St. to Wheaton St.) are being updated. Staff plans to meet with neighborhood groups when Phase 2 plans are complete. Plans will be submitted to permitting in May. It is anticipated that final plans and permits will be available in July. Construction is expected to start September 2018 and completed July 2019.

6/12/2018 11:18:31 AM:
Phase I (37th Street to Anderson St.) is complete. Plans for Phase II (Anderson St. to Wheaton St.) are being updated. Staff plans to meet with neighborhood groups when Phase 2 plans are complete. Plans will be submitted to permitting in May. It is anticipated that final plans and permits will be available in July. Construction is expected to start September 2018 and completed July 2019.

12/28/2017 2:42:02 PM:
Additional funding was included in the 2018 budget. Will work to get a contractor on board to do construct Phase 2.

11/6/2017 10:01:17 AM:
Phase I: Complete (37th Street to Anderson St.); Phase II (Anderson St. to Wheaton St.): waiting on funding

7/19/2017 6:50:07 PM:
Phase I: Complete (37th Street to Anderson St.); Phase II (Anderson St. to Wheaton St.): waiting on funding

3/31/2017 12:08:38 PM:
Phase I: Complete (37th Street to Anderson St.); Phase II (Anderson St. to Wheaton St.): waiting on funding

Last Project Update: 7/3/2019 11:47:31 AM
Fund(s): SPLOST V (2008-2014) | Contrbtn Frm Generl Fnd | SPLOST IV (2003-08) | Miscellaneous | State Of Georgia | SPLOST VI - District 2 Fund
Project Financial Data Last Updated On: 7/26/2019 3:39:54 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$5,281,030.58 $4,151,250.54 $924,562.44 $205,217.60


12/28/2017 2:42:02 PM