Scope:
To perform various park improvements in the Feiler Terrace Neighborhood. |
Comments:
|
11/24/2020 3:09:12 PM: Due to a lack of funding, the project is not expected to be implemented at this time.
7/20/2020 11:46:48 AM: Due to a lack of funding, the project is not expected to be implemented at this time.
3/26/2020 2:44:01 PM: Due to a lack of funding, the project is not expected to be implemented at this time.
12/23/2019 11:04:18 AM: The concept has been revised and a FEMA application prepared for submittal for sidewalks and a jogging trail on FEMA deed restricted properties.
10/7/2019 11:16:16 AM: The concept has been revised and a FEMA application prepared for submittal for sidewalks and a jogging trail on FEMA deed restricted properties.
7/12/2019 12:21:35 PM: The concept has been revised and a FEMA application prepared for submittal for sidewalks and a jogging trail on FEMA deed restricted properties.
4/12/2019 12:07:04 PM: The initial concept is being revised based on feedback received from the community. The scope of the project includes a sidewalk and walking/jogging trail around the perimeter of the FEMA lots and a bridge crossing the canal. The FEMA application is being prepared for submittal.
2/4/2019 11:53:26 AM: Scope of project will include a walking trail, benches, lighting and possibly drainage. Staff has created an initial draft concept.
11/5/2018 4:50:48 PM: Scope of project will include a walking trail, benches, lighting and possibly drainage.
7/9/2018 2:32:45 PM: The scope of project needs to be determined for park development in the Feiler Terrace neighborhood.
4/5/2018 5:18:40 PM: The scope of project needs to be determined for park development in the Feiler Terrace neighborhood.
4/5/2018 5:18:40 PM: The scope of project needs to be determined for park development in the Feiler Terrace neighborhood.
1/12/2018 2:50:54 PM: The scope of project needs to be determined for park development in the Feiler Terrace neighborhood.
11/3/2017 8:40:21 AM: The scope of work for this project and area has not been identified to proceed.
7/18/2017 4:44:34 PM: Staff currently in the process of confirming project scope.
3/31/2017 12:08:38 PM: Staff currently in the process of confirming project scope.
|
Last Project Update:
1/11/2021 9:53:33 AM |
Fund(s):
SPLOST VI - District 5 Fund |
Project Financial Data Last Updated On:
9/30/2020 3:07:44 PM |
Appropriated Budget To Date:
|
Expenditures To Date:
|
Open Purchase Orders:
|
Project Balance:
|
$2,675.00 |
$2,675.00 |
$0.00 |
$0.00 |
|

1/12/2018 2:50:54 PM
|