Capital Improvement Program

Project: Tompkins Center Renovation & Expansion Project No: PB0842 Status: Complete Category: Public Building Improvements
Location: 39th & Ogeechee Rd Start Year: 2013 End Year: 2017
Council District: 1 Project Manager: Barry Baker, Leif Blomberg BBaker@Savannahga.Gov;LBlomberg@savannahga.gov
Scope: Renovate and expand a portion of the existing building
Comments: 7/2/2019 4:00:15 PM:
Consultant purchase order has been adjusted. Record drawings and other close-out documentation will be finalized and distributed, and consultant agreement will be paid out before the end of 2019.

4/5/2019 5:08:21 PM:
Close-out documentation and final consultant agreement amendment is in process. The project is expected to close out in the 2nd quarter of 2019.

1/2/2019 10:54:13 AM:
Close-out documentation and final consultant agreement amendment is in process. The project is expected to close out in the 2nd quarter of 2019.

10/4/2018 5:13:03 PM:
Close-out documentation and final consultant agreement amendment is in process. The project is expected to close out in the 4th quarter of 2018.

7/11/2018 5:41:19 PM:
Although the project is complete, staff has been working on final warranty items and a final consultant agreement amendment. The project should be completely closed out the 3rd quarter of 2018.

4/5/2018 5:03:46 PM:
The Tompkins Center renovation and addition project is completed and the center re-opened in May 2017. Close-out documentation is in progress. The one-year warranty inspection was conducted on March 30.

4/5/2018 5:03:46 PM:
The Tompkins Center renovation and addition project is completed and the center re-opened in May 2017. Close-out documentation is in progress. The one-year warranty inspection was conducted on March 30.

1/2/2018 3:15:47 PM:
Tompkins Center renovation and addition complete and the center re-opened in May 2017. Close-out documentation is in progress.

11/13/2017 5:28:01 PM:
Tompkins Center renovation and addition has been completed and the Center re-opened in May 2017 with daily operation.

7/19/2017 5:21:13 PM:
Renovations have been performed; Center is now open; Project is complete.

3/31/2017 12:08:38 PM:
Replacement of pre-existing sanitary sewer is underway and a storm line extension is being installed; gym floor finisher being applied which will complete construction of project.

Last Project Update: 7/2/2019 4:00:15 PM
Fund(s): Contrbtn Frm Generl Fnd | SPLOST VI(2015-2020) | SPLOST VI - District 1 Fund
Project Financial Data Last Updated On: 7/26/2019 3:39:53 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$3,070,347.96 $3,067,306.12 $3,300.00 ($258.16)


1/2/2018 3:15:47 PM