Capital Improvement Program

Project: Bomb Squad Roof Replacement Project No: PB0240 Status: Complete Category: Public Building Improvements
Location: NULL Start Year: 2016 End Year: 2018
Council District: N/A Project Manager: Asst. Chief Gavin RGavin@Savannahga.Gov
Scope: Replace roof on SCMPD Bomb Squad facility
Comments: 7/12/2019 8:27:39 AM:
The warranty has been confirmed and the project is complete. Remaining funds are being transferred to another project.

4/10/2019 12:36:11 PM:
The warranty has been confirmed and the project is complete. Remaining funds are being transferred to another project.

1/4/2019 12:09:59 PM:
The warranty has been confirmed and the project is complete. Remaining funds are being transferred to another project.

10/4/2018 4:49:35 PM:
Work is completed. Warranty is being processed. Remaining funds are being transferred to another project.

7/17/2018 10:27:05 AM:
Completion of the initial phase of roof replacement work is expected in July. FEMA-funded insulation replacement work will occur after roof replacement is complete.

6/12/2018 11:30:12 AM:
Completion of the initial phase of roof replacement work is expected in July. FEMA-funded insulation replacement work will occur after roof replacement is complete.

6/12/2018 11:30:12 AM:
Completion of the initial phase of roof replacement work is expected in July. FEMA-funded insulation replacement work will occur after roof replacement is complete.

1/2/2018 11:08:03 AM:
This project needs to be reviewed and evaluated by the Chief of Police.

10/24/2017 10:35:24 AM:
This project needs to be reviewed and evaluated by the Chief of Police.

7/19/2017 6:26:43 PM:
Additional funding needed for project completion.

3/31/2017 12:08:38 PM:
Project scheduled to begin in May 2017 and is expected to be completed by June 2017.

Last Project Update: 7/12/2019 8:30:50 AM
Fund(s): Contrbtn Frm Generl Fnd | SPLOST VI - District 5 Funds | SPLOST V (2008-2014
Project Financial Data Last Updated On: 7/26/2019 3:39:52 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$98,328.56 $73,900.00 $0.00 $24,428.56


1/2/2018 11:08:03 AM