Scope:
To backup and upgrade system in the E911 back up center |
Comments:
|
1/25/2019 3:44:25 PM: The 911 Transition to the county is still ongoing. The county will influence further discussions for needs for continuity of operations and how the backup 911 Center will be used going forward. Project is being closed out.
10/26/2018 1:34:20 PM: The 911 Transition project will influence further discussions for needs for continuity of operations and how the backup 911 Center will be used going forward.
7/9/2018 5:50:04 PM: The 911 Transition project will influence further discussions for needs for continuity of operations and how the backup 911 Center will be used going forward.
4/17/2018 5:57:40 PM: The upgrade to the VIPER system at the backup 911 Center was completed in First Quarter 2018. The 911 Transition project will influence further discussions for needs for continuity of operations and how the backup 911 Center will be used going forward.
4/17/2018 5:57:40 PM: The upgrade to the VIPER system at the backup 911 Center was completed in First Quarter 2018. The 911 Transition project will influence further discussions for needs for continuity of operations and how the backup 911 Center will be used going forward.
1/5/2018 5:28:20 PM: The VIPER upgrade project is scheduled to be completed in March 2018. Further evaluation of solutions needed for continuity of operations will be evaluated once this upgrade has been completed.
10/6/2017 10:01:27 AM: The VIPER upgrade project is scheduled to be completed in March 2018. Further evaluation of solutions needed for continuity of operations will be evaluated once this upgrade has been completed.
6/30/2017 6:28:10 PM: A contract was signed with ATT in June 2017 to upgrade the VIPER system that manages 911 calls. A kick-off meeting for this project is expected to be scheduled in July 2017. The implementation of the VIPER upgrade will further dictate solutions for continuity of operations at the backup e911 Center. Anticipate these plans will be formulated in the 3rd quarter 2017.
3/31/2017 12:08:38 PM: This project has been on-hond pending SCMPD/IT to finalize best solution for continuity of operations at the backup e911 Center. We have resumed discussions with vendors to determine the best solution and will develop plan and schedule.
|
Last Project Update:
1/25/2019 3:44:25 PM |
Fund(s):
SPLOST V (2008-2014 |
Project Financial Data Last Updated On:
1/28/2019 12:24:48 PM |
Appropriated Budget To Date:
|
Expenditures To Date:
|
Open Purchase Orders:
|
Project Balance:
|
$356,570.95 |
$356,570.95 |
$0.00 |
$0.00 |
|

1/5/2018 5:28:20 PM
|