Capital Improvement Program

Project: Pedestrian Wayfinding Signage Project No: OP0145 Status: Implementation/Construction Category: Other Improvements
Location: Historic Downtown District Start Year: 2015 End Year: 2019
Council District: 2 Project Manager: Bridget Lidy blidy@Savannahga.Gov
Scope: Wayfinding signage for visitors
Comments: 7/8/2019 11:17:47 AM:
Phase 2 signs were installed in the 4th quarter. Several signs require adjustments such as painting the screws and adding finials. Adjustments are expected to be completed in the 3rd quarter.

4/5/2019 9:08:21 AM:
Phase 2 signs were installed in the 4th quarter. Several signs require adjustments such as painting the screws and adding finials. Adjustments are expected to be completed in the 2nd quarter.

1/4/2019 9:18:41 AM:
Phase 2 signs were installed in the 4th quarter. Several signs require adjustments such as painting the screws and adding finials. Adjustments will be completed in the 1st quarter.

10/9/2018 11:02:29 AM:
Phase 2 signs are fabricated and installation has commenced. Delays were encountered during installation and completion is expected in October 2018. Phase 3 will go out to bid upon completion of Phase 2 and will include the fabrication and installation of 4 Historic District Gateway (Large), 2 Historic District Gateway River Street and 8 Historic District Gateway Boundary Markers, and 10 trailblazers.

7/9/2018 3:03:29 PM:
By the end of the 3rd Quarter, Phase 2 will be fabricated and installed. This includes 23 parking directional signs, 3 district signs, 3 vehicular directional signs, and 2 river street entry signs. Two of the signs (#54 and #205) will be installed at a later date. Sign #54, intended for W Bay at Scarborough, will be installed once construction of the Bay Street Widening is completed. Sign #205 will be relocated to State Street. Phase 3 will go out to bid in the 3rd Quarter and include the fabrication and installation of 4 Historic District Gateway (Large), 2 Historic District Gateway River Street and 8 Historic District Gateway Boundary Markers, and 10 trailblazers.

4/13/2018 3:01:56 PM:
The 32 signs have been fabricated and will be installed in the 2nd Quarter of 2018. Delays were encountered during the final sign location review process.

4/13/2018 3:01:56 PM:
The 32 signs have been fabricated and will be installed in the 2nd Quarter of 2018. Delays were encountered during the final sign location review process.

12/28/2017 8:52:18 AM:
The 32 signs have been fabricated and will be installed in the 1st Quarter of 2018. Delays were encountered due to scheduling conflicts with the contractor.

10/6/2017 12:41:37 PM:
The 32 signs have been fabricated and will be installed during the 4th Quarter 2017. Delays were encountered during fabrication phase.

7/20/2017 3:48:57 PM:
32 wayfinding signs are in process of being installed to direct visitors to municipally owned parking facilities. This phase is expected to be completed by the second 3rd quarter of 2017. Additional phases will follow once implementation of parking signs occur.

3/31/2017 12:08:38 PM:
Second phase of this project is underway and includes the fabrication and installation of 32 wayfinding signs.  This phase is expected to be completed by the second quarter of 2017. Additional phases will follow.

Last Project Update: 7/8/2019 11:17:47 AM
Fund(s): SPLOST VI(2015-2020) | Parking Svcs Fun
Project Financial Data Last Updated On: 7/26/2019 3:39:49 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$700,000.00 $109,779.20 $25,060.80 $565,160.00