Capital Improvement Program

Project: Casey South Drainage Improvements Phase II Project No: DR0911 Status: Design/Pre-Construction Category: Drainage Improvements
Location: 55th St to North, Harmon to East, 63rd St to South, and Abercorn to West Start Year: 2005 End Year: TBD
Council District: 3,4,5 Project Manager: Roger Raines RRaines@Savannahga.Gov
Scope: To increase drainage capacity in the Casey South basin
Comments: 7/2/2019 3:08:19 PM:
60% design plans were received from the consultant during the quarter. A public meeting is scheduled for July 11 to discuss design details on Columbus Drive.

3/29/2019 2:24:48 PM:
Staff continues to await delivery of the 60% design plans. Staff is also reviewing project options regarding tree canopy along Columbus Drive. Greenscapes staff are assisting with the review.

12/31/2018 4:37:57 PM:
Thomas and Hutton delivered 30% plans and 30% Stormwater Management Report. This entry corrects a typo on last quarter's report. Staff received a signed and sealed hydraulic model report from EMC in November. Traffic calming analysis for Hull Park indicates that a raised crosswalk is the most practical traffic calming technique for the design. Staff also received the Preliminary Estimation and review of Construction Vibration Levels for Driven Sheet Piles for Temporary Excavation Support report and has begun review. Thomas and Hutton is completing 60% construction plans.

10/12/2018 12:22:48 PM:
Thomas & Hutton delivered 90% design plans and is finalizing design of traffic calming structures for the South end of Hull Park. Bidding of the project is scheduled for second quarter 2019 with construction to be complete by late 2022.

7/12/2018 4:10:38 PM:
Consultant Thomas & Hutton completed the pre-concept phase of the design, delivered 30% completion design drawings, and is working on detailed design. Staff is reviewing the 30% design submittal. Consultant is several months behind schedule, but believes they can deliver completed design by 1Q 2019. Construction to be complete by 2022.

6/12/2018 11:13:53 AM:
Consultant conducted survey and soil boring work during the first quarter. Geotechnical work is underway, and a pre concept meeting with Staff is set during mid April. Completion of the design phase and start of the bid process is expected in the first quart of 2019. Bid opening, contract award and start of construction is expected in the second quarter of 2019 and completion in fourth quarter of 2021.

6/12/2018 11:13:53 AM:
Consultant conducted survey and soil boring work during the first quarter. Geotechnical work is underway, and a pre concept meeting with Staff is set during mid April. Completion of the design phase and start of the bid process is expected in the first quart of 2019. Bid opening, contract award and start of construction is expected in the second quarter of 2019 and completion in fourth quarter of 2021.

12/27/2017 10:06:29 AM:
Consultant Thomas & Hutton has initiated survey and soil boring work as the design work continues.

10/24/2017 9:29:04 AM:
Consultant Thomas & Hutton awarded design contract and has begun design work.

6/14/2017 1:46:44 PM:
Request to award design services of this improvement is on draft Council Agenda for early July.

3/31/2017 12:08:38 PM:
Design RFP should be advertised in January 2017

Last Project Update: 7/2/2019 3:08:21 PM
Fund(s): SPLOST IV (2003-08) | Contrbtn Frm Generl Fnd | Frm Drng SPLOST (1998-2003) | SPLOST Other Cip (1998-2002) | SPLOST V (2008-2014
Project Financial Data Last Updated On: 7/26/2019 3:39:48 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$18,224,525.84 $1,894,904.86 $1,155,939.15 $15,173,681.83


12/27/2017 10:06:29 AM