Capital Improvement Program

Project: Brick Line Replacement Project No: DR0505 Status: Ongoing Category: Drainage Improvements
Location: City-wide Start Year: 2010 End Year: Annual
Council District: City-Wide Project Manager: Ken Kelly kkelly@Savannahga.Gov
Scope: Annual CIP to fund necessary replacement/rehabilitation of deteriorating aging brick storm lines with concrete pipe or structural liner. Projects to date have addressed point failures on brick lines primarily in the Historic District. As the failures crop up unexpectedly, the annual fund was set up to have an accout available for the rehabilitations.
Comments: 11/16/2021 1:08:23 PM:
This CIP account recently received new funding in the amount of $500,000.00. Pursuant to the receipt of this new funding, a needed brick drainage pipe lining project was identified on West 36th Street from MLK to Bull Street. Completion of this project will help alleviate flooding in the West 36th Street corridor with particular emphasis on the MLK and West 37th Street area. This project is currently in progress with Southeast Pipe Survey, Inc. working to clean and televise the 36" diameter brick storm line on 36th Street between MLK and Bull Street.

8/17/2021 10:14:24 AM:
This CIP account recently received new funding in the amount of $500,000.00. Pursuant to the receipt of this new funding, a needed brick drainage pipe lining project was identified on West 36th Street from MLK to Bull Street. Completion of this project will help alleviate flooding in the West 36th Street corridor with particular emphasis on the MLK and West 37th Street area. This project is slated to begin in September of 2021 with expected completion by the end of 2021.

4/30/2021 11:11:21 AM:
Although this is an annual fund to keep up with necessary repairs to aging brick lines, it has not received any contributions for several budget years. This project was set up as an annual fund to accumulate funding for Brick Line Replacements/Lining as needed for replacements. Brick lines are the oldest stormlines the City maintains.

12/9/2020 8:55:35 AM:
Although this is an annual fund to keep up with necessary repairs to aging brick lines, it has not received any contributions for several budget years. This project was set up as an annual fund to accumulate funding for Brick Line Replacements/Lining as needed for replacements. Brick lines are the oldest stormlines the City maintains.

7/13/2020 10:29:06 AM:
Although this is an annual fund to keep up with necessary repairs to aging brick lines, it has not received any contributions for several budget years. This project was set up as an annual fund to accumulate funding for Brick Line Replacements/Lining as needed for replacements. Brick lines are the oldest stormlines the City maintains.

3/16/2020 11:01:47 AM:
Although this is an annual fund to keep up with necessary repairs to aging brick lines, it has not received any contributions for several budget years. This project was set up as an annual fund to accumulate funding for Brick Line Replacements/Lining as needed for replacements. Brick lines are the oldest stormlines the City maintains.

12/19/2019 3:54:03 PM:
Although this is an annual fund to keep up with necessary repairs to aging brick lines, it has not received any contributions for several budget years. This project was set up as an annual fund to accumulate funding for Brick Line Replacements/Lining as needed for replacements. Brick lines are the oldest stormlines the City maintains.

9/30/2019 12:58:41 PM:
Although this is an annual fund to keep up with necessary repairs to aging brick lines, it has not received any contributions for several budget years. This project was set up as an annual fund to accumulate funding for Brick Line Replacements/Lining as needed for replacements. Brick lines are the oldest stormlines the City maintains.

7/2/2019 3:02:47 PM:
Although this is an annual fund to keep up with necessary repairs to aging brick lines, it has not received any contributions for several budget years. This project was set up as an annual fund to accumulate funding for Brick Line Replacements/Lining as needed for replacements. Brick lines are the oldest stormlines the City maintains.

3/29/2019 2:20:39 PM:
This project was set up as an annual fund to accumulate funding for Brick Line Replacements/Lining as needed for replacements. Brick lines are the oldest stormlines the City maintains.

1/14/2019 10:22:15 AM:
This project was set up as an annual fund to accumulate funding for Brick Line Replacements/Lining as needed for replacements. Brick lines are the oldest stormlines the City maintains.

10/2/2018 1:38:22 PM:
Lining of the old brick line beneath Pulaski Square was recently completed.

7/3/2018 1:41:41 PM:
Set up as an annual fund to accumulate funding for Brick Line Replacements/Lining as needed for replacements. New lining project in Laurel Grove North cemetery along Ogeechee Road to be undertaken as soon as new annual lining contract is executed and released for use.

4/2/2018 11:37:54 AM:
Set up as an annual fund to accumulate funding for Brick Line Replacements/Lining as needed for replacements. New lining project in Laurel Grove North cemetery along Ogeechee Road to be undertaken as soon as new annual lining contract is bid and awarded.

4/2/2018 11:37:54 AM:
Set up as an annual fund to accumulate funding for Brick Line Replacements/Lining as needed for replacements. New lining project in Laurel Grove North cemetery along Ogeechee Road to be undertaken as soon as new annual lining contract is bid and awarded.

1/9/2018 10:08:16 AM:
Set up as an annual fund to accumulate funding for Brick Line Replacements/Lining as needed for replacements. New lining project in Laurel Grove North cemetery along Ogeechee Road to be undertaken as soon as new annual lining contract is bid and awarded.

10/9/2017 2:53:40 PM:
Set up as an annual fund to accumulate funding for Brick Line Replacements/Lining as needed for replacements.

7/1/2017 12:00:00 AM:
Set up as an annual fund to accumulate funding for Brick Line Replacements/Lining as needed for replacements.

3/31/2017 12:08:38 PM:
Set up as an annual fund to accumulate funding for Brick Line Replacements/Lining as needed for replacements.

Last Project Update: 12/9/2020 8:55:35 AM
Fund(s): Contrbtn Frm Generl Fnd | SPLOST IV (2003-08) | Miscellaneou
Project Financial Data Last Updated On: 9/30/2020 3:07:44 PM
Appropriated Budget To Date: Expenditures To Date: Open Purchase Orders: Project Balance:
$406,869.86 $286,764.81 $0.00 $120,105.05


1/9/2018 10:08:16 AM